600 EP retrofit unlocks Big4 Yamba expansion

Klaro engineering replaced an undersized, odorous system at a popular holiday park.

Big4 Saltwater Holiday Park · Yamba, NSW

600 EP

Treatment capacity

UV + chlorine

Dual disinfection

Remote

Monitoring

Project data

Location
Yamba, NSW
Region
Australia
Sector
Sports
Solution
Wastewater treatment
Product
Klaro
Source
KLARO
Purpose
Holiday park wastewater
Capacity
600 EP
Disinfection
UV + chlorine
Consultant
Whitehead & Associates

Challenge

Big4 Saltwater's wastewater system was undersized, odorous and unable to balance peak holiday-season loads, blocking development expansion at a high-demand coastal park.

Solution

Whitehead & Associates confirmed the failure and GRAF engineered a 600 EP replacement with UV and chlorine disinfection, remote monitoring and PAC dosing for phosphorus removal.

Outcomes

  • 600 EP capacity for peak holiday loads
  • Dual disinfection with remote monitoring
  • Expansion plans unlocked for the park