GRAF Australia
600 EP retrofit unlocks Big4 Yamba expansion project photo, Yamba, NSW
WastewaterSportsWastewater treatment Klaro

600 EP retrofit unlocks Big4 Yamba expansion

Klaro engineering replaced an undersized, odorous system at a popular holiday park.

Big4 Saltwater Holiday Park · Yamba, NSW

600 EP

Treatment capacity

UV + chlorine

Dual disinfection

Remote

Monitoring

Project data

Location
Yamba, NSW
Region
Australia
Sector
Sports
Solution
Wastewater treatment
Product
Klaro
Source
KLARO
Purpose
Holiday park wastewater
Capacity
600 EP
Disinfection
UV + chlorine
Consultant
Whitehead & Associates
01

Challenge

Big4 Saltwater's wastewater system was undersized, odorous and unable to balance peak holiday-season loads, blocking development expansion at a high-demand coastal park.

02

Solution

Whitehead & Associates confirmed the failure and GRAF engineered a 600 EP replacement with UV and chlorine disinfection, remote monitoring and PAC dosing for phosphorus removal.

03

Outcomes

  • 600 EP capacity for peak holiday loads
  • Dual disinfection with remote monitoring
  • Expansion plans unlocked for the park

Project Gallery

Planning something similar?

600 EP retrofit unlocks Big4 Yamba expansion